Fitting a run of four to eight toilet cubicles usually takes one to two days once the room is ready. Allow one to two weeks from enquiry to survey and quotation, and two to four weeks for manufacture after drawings are signed off, so most cubicle projects complete within four to seven weeks.
Installer fixing an adjustable stainless steel leg to a navy cubicle panel Illustrative image
Typical programme
Stage
Typical duration
Enquiry to survey
A few days to two weeks
Quotation and drawing sign-off
Up to a week
Manufacture
2–4 weeks
Installation of 4–8 cubicles
1–2 days
Full washroom refurbishment on site
1–3 weeks
How to speed things up
Send dimensions and photos with your enquiry.
Choose standard colours, which are usually quicker to manufacture.
Make sure the floor, walls and plumbing are finished before cubicles are fitted.
Written by the Washroom Cubicles technical team. We design and install commercial washrooms across England, Scotland and Wales. Last reviewed 8 October 2026. Regulations change, so confirm requirements for your project with your building control body.
Frequently asked questions
Can you install over a weekend?
Yes. Most cubicle runs can be fitted over a weekend so the washroom is back in use on Monday.